Creating Sustainable Change in Downtown San Francisco

Creating Sustainable Change in Downtown San Francisco
By Samantha Serafica

Rendering showing completed improvements on 6th Street between Market and Howard Streets

Rendering of 6th Street between Market and Howard Streets

When planning for new projects in Downtown San Francisco, the SFMTA must look at potential sites through multiple lenses:  

  • How did previous planning decisions that funnel traffic through the Tenderloin to freeway onramps in SoMa influence existing street conditions?  

  • How can we leverage quick-builds and capital streetscape projects now to make the streets safer not only today, but far into the future as well? 

This dual-pronged approach allowed the SFMTA to address immediate safety issues along 6th and Taylor streets while collaborating with San Francisco Public Works to bring capital improvements to these corridors. 

6th and Taylor streets are among the 13%  of city streets that account for 75% of severe traffic injuries and fatalities known as the Vision Zero high-injury network. The communities that live along these corridors largely consist of seniors, children, people with disabilities, limited English proficient people, and lower-income families—all of whom face higher risks of traffic collisions resulting in injury and/or death.  

Both the 6th Street Pedestrian Safety and Safer Taylor Street projects were legislated in the fall of 2018. Within a year, the SFMTA constructed its first quick-build improvements along 6th and Taylor streets to address critical pedestrian safety needs. These included: 

  • Travel lane reconfigurations to calm traffic and limit last minute lane changes 

  • Signal changes and left-turn restrictions to manage traffic flow and reduce collisions 

  • Curb management and buffered parking lanes to prioritize passenger and commercial loading zones 

  • Painted safety zones and daylighting to slow fast turning vehicles and improve visibility of people walking  

These changes reduced opportunities for conflict between motorists and sidewalk users while accommodating the community’s various street usages. After implementation, evaluation showed a 21% decrease in vehicle speeds on average along 6th Street, and a 100% reduction in double parking along Taylor Street. Larger capital projects take time to design and bid, but the SFMTA did not have to compromise on street safety. The quick-build improvements were installed while the projects’ construction-heavy streetscape elements were still being refined. 

Photo rendering showing completed improvements on Taylor Street between Turk and Ellis StreetsRendering of Taylor Street between Turk and Ellis Streets 

While quick-builds address many of the immediate traffic safety needs, capital streetscape improvements like signal upgrades and landscape amenities will improve the quality of life by allowing protected and dedicated crossing times for people walking and creating inviting spaces. Many downtown residents live in small quarters like single-resident occupancy (SRO) properties, often with little to no outdoor space. The sidewalks along these corridors often function as an extension of people’s homes. Widening the sidewalks will enhance the space and allow a clear path of travel, especially for those using mobility devices, like wheelchairs.  

Capital improvements also allow for more possibilities to incorporate community elements and identity. 6th Street is part of the Filipino Cultural District, and both 6th and Taylor streets are part of the Transgender District, the first legally recognized transgender district in the world. Throughout the detailed design phase, we have been working closely with local groups such as SOMA Pilipinas and The Transgender District to implement community-identifying decorative crosswalks. These improvements will build off the previous quick-build work to further enhance safety and livability for people walking along these corridors.  

Since fall 2018, the SFMTA and Public Works teams have been diligently designing construction plans that include sidewalk widening with corner bulb-outs to shorten crossing distances and reduce speeds of turning vehicles, new and upgraded utilities and traffic signals and streetscape amenities such as new trees, benches, and decorative crosswalks. 

These project elements will continue to enhance the walking, biking, shopping, and living experiences of the 6th and Taylor Street communities. Due to unique issues below street level involving utilities and sub-sidewalk basements along the project corridors, these projects will require extensive construction.  

While the SFMTA led the planning and legislation processes of these projects, we will be handing the baton to San Francisco Public Works to manage implementation and construction communication. As construction begins, both agencies will continue to reach out to the community to minimize disruption to merchants, residents, and visitors along 6th and Taylor streets. For more information, please visit SFMTA.com/6thSt and SFMTA.com/Taylor



Published July 31, 2021 at 05:53AM
https://ift.tt/3rNZt6L

Comments

Popular posts from this blog

New top story from Time: ‘It’s a Catastrophe.’ Iranians Turn to Black Market for Vaccines as COVID-19 Deaths Hit New Highs

https://ift.tt/3AODY94 In January, Iranian Supreme Leader Ayatollah Ali Khamenei made the sudden announcement that American and British-made COVID-19 vaccines would be “forbidden” as they were “completely untrustworthy.” Almost nine months later, Iran is facing its worst surge in the virus to date — a record number of deaths and infections per day with nearly 4.2 million COVID-19 patients across the country , and a healthcare system near collapse. “It’s a catastrophe; and there is nothing we can do,” said an anesthesiology resident in one of Tehran’s public hospitals who due to the current surge is tasked to oversee the ICU ward for COVID-19 patients. “We can’t treat them nor help them; so all I can ask people to do is to stay home and do whatever it takes to not get exposed.” The doctor requested anonymity in order to speak freely; others interviewed by TIME asked to be identified only by their first name. [time-brightcove not-tgx=”true”] The scale of the crisis is such ...

BRT Service on Van Ness to Begin Tomorrow

BRT Service on Van Ness to Begin Tomorrow By Jiaying Yu Tomorrow, April 1, we will cut the ribbon on San Francisco’s first Bus Rapid Transit (BRT) corridor on Van Ness Avenue. The public is invited to join and celebrate this historic moment in front of the War Memorial. The ribbon-cutting will include speeches from local and state leaders, performances from local musicians and giveaways. After the ribbon is cut, there will be an inaugural ride on the new Van Ness BRT corridor to North Point where the celebration continues with live music.    BRT service on Van Ness is part of Muni’s Rapid Network, which prioritizes frequency and reliability for customers. Muni and Golden Gate Transit customers are expected to experience 32% shorter travel times. With dedicated transit lanes in the middle of the road, enhanced traffic signals with Transit Signal Priority and new platforms and shelters, the Van Ness BRT corridor will be the fastest way to travel north-south in this part of...

Ride to Chase Center Events Along the New T Third

Ride to Chase Center Events Along the New T Third By Christopher Ward Starting January 7, take the S Shuttle Mission Bay on the new T Third line via Central Subway to Chase Center events. Service on the new T Third Line from Chinatown Rose-Pak to Sunnydale starts January 7. With it , new event service to Chase Center will also start via Central Subway on the S Shuttle Mission Bay. During events at Chase Center, shuttles will operate between Chinatown-Rose Pak Station and UCSF/Chase Center every 10 minutes. These shuttles will start approximately two and a half hours before an event and continue for two and half hours after an event. From Chinatown to Chase Center, riding the S Shuttle Mission Bay takes about 20 minutes. Best of all, your Chase Center event ticket is your Muni fare. No additional Muni fare needed ! Both electronic and physical tickets for events – including Warriors games, concerts and other events – will serve as  proof of payment  for Muni serv...

Supreme Court to hear plea against UGC guidelines today as students oppose circular on final year exams https://ift.tt/30023ug

The Supreme Court on Monday is set to hear petitions challenging the UGC guidelines, which made it mandatory for universities to conduct their final year exams by September 30. The petitions would be heard by a three-judge bench of the top court, comprising of Justices Ashok Bhushan, R Subhash Reddy and MR Shah. The plea was filed by 31 students across several universities in India. The students, in their petition, had challenged the UGC guidelines for being arbitrary as it would compel students to appear for exams amid the COVID-19 pandemic. 

Replacing Parking Meters with (Actual) Bike Parking

Replacing Parking Meters with (Actual) Bike Parking By Eillie Anzilotti Did you know you can submit a request for new bike parking? Anyone who rides a bike in San Francisco knows: A parking meter is not just a parking meter. Like street sign poles, meters are also a place to lock your bike when you’re out running errands and exploring the city.  As an agency, we’re working towards the goal of making bike racks and corrals available across the city, wherever people need them. In the meantime, we recognize that informal bike and scooter parking options, like parking meters, meet people’s needs.   So, when we announced a campaign last year to remove existing parking meters and replace them with pay stations, this brought up a question: what does this mean for bike parking?  We strive to install bike racks to replace parking options wherever meters are removed. Right now, our bike parking team is focused on identifying locations for new racks in high-demand areas ...

FOX NEWS: Intermittent fasting may cause muscle loss more than weight loss, study says Intermittent fasting might not be as healthy as some may have thought.

Intermittent fasting may cause muscle loss more than weight loss, study says Intermittent fasting might not be as healthy as some may have thought. via FOX NEWS https://ift.tt/2ShpJp3

New T Third Connecting Chinatown to Sunnydale Starts Saturday

New T Third Connecting Chinatown to Sunnydale Starts Saturday By Christopher Ward New Muni Metro map. This Saturday the T Third starts its long-awaited new route connecting Chinatown-Rose Pak Station from 4th & King in Central Subway, Mondays through Fridays, 6 a.m. to midnight every 10 minutes and Saturdays and Sundays, 8 a.m. to midnight every 12 minutes.   The K Ingleside will now travel between Balboa Park and Embarcadero Station. Customers using Embarcadero & Folsom, Embarcadero & Brannan and 2nd and King platforms should transfer to the N Judah at Powell Station or 4th & King. Watch the new Muni Metro service  map animations . The following bus service changes also start this Saturday: The T Third Bus will now run along 3rd and 4th Streets in SoMa and on Stockton Street north of Market Street to align with the new T Third rail line and will no longer travel on the Embarcadero and Market Street.   The 6 Haight/Parnassus  will now...

How To Navigate Transfers on the New T Third

How To Navigate Transfers on the New T Third By Mariana Maguire SFMTA Ambassadors are helping customers navigate the new Central Subway stations and Metro service changes. As we prepare for the start of new T Third service on Saturday, January 7, between Sunnydale and Chinatown-Rose Pak Station, here are some important travel tips to help you plan your new connections. New T Third service via Central Subway starts January 7 with service between Sunnydale and Chinatown-Rose Pak Station. For J Church, K Ingleside, M Ocean View Customers For stops along the Embarcadero and King Street including 2nd & King (Oracle Park) and 4th & King (Caltrain), take the N Judah. For service north to Chinatown-Rose Pak Station or south to Yerba/Buena Moscone Station, 4th & King streets (Caltrain), UCSF/Chase Center and beyond to Sunnydale, transfer at Powell Station to Union Square/Market Street Station and take the new T Third. The N Judah will also continue to serve 4th & King ...

FOX NEWS: Top baby names list for 2021 reveals familiar trends For the second year in a row, these two names are the most popular for girls and boys – leading BabyCenter's Top 100 Baby Names list.

Top baby names list for 2021 reveals familiar trends For the second year in a row, these two names are the most popular for girls and boys – leading BabyCenter's Top 100 Baby Names list. via FOX NEWS https://ift.tt/CFenBRh

New top story from Time: George Floyd Was ‘Terrified, Scared,’ Says Witness Who Recorded Derek Chauvin Kneeling on His Neck

https://ift.tt/3dcqgTi Darnella Frazier, the teenage witness who took the famous video of George Floyd being crushed into the ground by Minneapolis police officer Derek Chauvin on May 25, 2020, took the stand in Chauvin’s trial on Tuesday and described Floyd as a “man terrified, scared, begging for his life.” Frazier, who was 17 when the incident took place, was not shown on camera and only her voice was heard during her testimony. In the midst of her testimony, Frazier was soft-spoken and at times wept she when she recounted the events of that day. She told the prosecutor that on May 25, she was walking to the Cup Foods grocery store with her 9-year-old cousin to get some snacks. Outside the store, she saw Floyd on the ground with Chauvin on top of him and told her cousin to go inside the store so that the younger child would not see what was happening. “I heard George Floyd saying I can’t breathe, please get off of me. I can’t breathe. He cried for his mom. He was in ...